Updated How long does it take to implement an AI SDR?
Realistic timeline by segment
SMB (1 week): SaaS default deployment. Point at your docs, connect Salesforce or HubSpot, turn on. Skip shadow mode.
Mid-market (2–4 weeks):
- Week 1: knowledge base ingestion, prompt tone tuning, first internal test conversations.
- Week 2: CRM field mapping, routing rules per AE, escalation paths.
- Week 3: shadow mode on real traffic (AI drafts, human reviews before send).
- Week 4: live on a traffic slice (usually /pricing and /demo first).
Enterprise (6–10 weeks):
- Add 2 weeks for security review + SSO setup.
- Add 2 weeks for multi-region tenant provisioning.
- Add 1 week for enablement across 20+ AEs.
See the full implementation checklist with RACI, tools, and week-by-week task list.
Related questions
Who owns the implementation internally?
RevOps owns the deploy. Marketing feeds knowledge base and messaging. Sales enables handoff. IT/security signs off on data flow. See the role playbooks for exact RACI.
Can I self-serve the deployment?
For SMB tiers, yes. For anything above 10 AEs, no — the routing rules alone need a human. Assume a Customer Success rep from the vendor for at least the first month.